What civil engineering work was required for the High-Luminosity LHC?
The new equipment for the High-Luminosity LHC requires new, large, civil-engineering structures on the sites of the ATLAS experiment in Meyrin, Switzerland (LHC Point 1) and the CMS experiment in Cessy, France (LHC Point 5).
On each site, the underground constructions consist of:
- A vertical shaft around 80 m deep and 10 m in diameter
- An underground service cavern (16 m in diameter and 46 m long) that will notably house cryogenics, cooling and ventilation equipment
- A 300-metre-long gallery for accelerator equipment and infrastructures, including power converters, protection systems, electrical distribution boxes, beam instrumentation and accelerator controls
- Four galleries measuring around 50 metres in length, connecting the new structures to the LHC accelerator tunnel. These will house specific hardware, such as radiofrequency equipment for the crab cavities, superconducting links and cryogenic distribution lines.
The connection to the LHC tunnel will be made via 14 vertical cores (each around 1 m in diameter and 7 m deep) located at the end of the connecting galleries, 7 on either side of the Interaction Point (IP), which will be drilled later and completed during Long-Shutdown 3.
On each site, the surface structure consists of five new buildings, representing a total surface area of 2800 m2. These will house the cooling and ventilation equipment, cryogenic equipment, as well as electrical equipment supplying the new accelerator equipment installed underground.
Who carried out the work?
The HL-LHC civil engineering project is based on four main contracts. Two consultancy service contracts are dedicated to the design and to the construction administration: SETEC–CSD–ROCKSOIL (ORIGIN) at Point 1 and LOMBARDI–ARTELIA–PINI (LAP) at Point 5. Two supply contracts are dedicated to the construction of both the underground and surface structures: MARTI TUNNELBAU - MARTI ÖSTERREICH - MARTI DEUTSCHLAND (JVMM) at Point 1 and IMPLENIA SCHWEIZ - BARESEL - IMPLENIA CONSTRUCTION (CIB) at Point 5. Each employed up to 70 people on each site during peak periods.
What was the work schedule?
The HL-LHC civil engineering works began in May 2018 and lasted about five years. All foreseen underground and surface works were successfully completed in September 2022 at Point 1 and in December 2022 at Point 5.
What happened to the excavated materials?
In total, 92,000m3 of soil were excavated from the underground structures on both sites. The excavated material was analysed on the surface to check its quality; the soil polluted by hydrocarbon was managed accordingly. On the Meyrin site, much of the excavated material was reused to create a platform on which the surface buildings were erected. The rest was taken to a treatment centre. At Cessy, almost all the excavated material was taken to inert waste storage facilities located less than 20 km from the worksite, to limit the transport distance. On both sites, the topsoil was reused for landscaping.
How did the work affect the environment?
The contracts concluded with the two civil-engineering consortia imposed environmental restrictions, including the hiring of experts to perform environmental monitoring on the worksite.
- Noise
The noise generated by the work was limited to respect French and Swiss regulations. An acoustic system monitored noise levels at various times. Measures were taken to limit noise, such as the construction of a temporary building with noise barriers above each shaft to minimise noise pollution from the excavation, or the installation of mufflers on the ventilation systems for the underground work. Surface work took place only on working days, during the day.
- Light pollution
To limit light pollution at Point 5, it was decided to limit the worksite lighting during the nights to the minimum compatible with the safety of the workers.
- Air
Host State regulations govern the release of dust into the air while the work is taking place. Measures were implemented, such as a wheel-washing system for lorries leaving the sites, vehicle speed restrictions and a sprinkler system in dry weather.
- Water
A worksite water management plan was established to prevent pollution. The excavation areas were protected from rainwater, as far as possible. A water treatment plant was installed on each site to treat all water coming from the worksite before it was discharged. The water quality was monitored.
Will there be any long-term environmental impact?
- Traffic
Now that the work is complete, the footpath in Meyrin linking the Maisonnex sports complex to the Chemin de la Berne has been reopened, with the route modified to pass around the new buildings. The footpath in Cessy remains unchanged.
- Landscaping
Both sites were landscaped and planted with around twenty local tree species.
- Noise
An acoustic survey of the future facilities was performed and formed part of the permission requirements. Noise emissions remain below the legal limits. All the new equipment for the HL-LHC will be installed either in surface buildings with soundproofing or underground.
- Water
In Meyrin, a new water retention tank was installed to regulate the flow of rainwater into the Nant d’Avril stream. A new monitoring station was set up (CERN has 27 water monitoring stations on its sites and the surrounding areas). A similar tank is already in operation in Cessy, regulating the water released into the Oudar. In Cessy, two water tables are located beneath the experiment site. The work only penetrated the surface water table: a watertight, circular wall was installed to a depth of 15 metres to isolate the water table and make it possible to excavate inside it. The work did not penetrate the deeper water table.
What energy consumption is required for the High-Luminosity LHC?
The new HL-LHC equipment will require a total electrical power of 17 MW and will increase during operation the CERN electrical consumption by about 9 %.