News
News
First LHC sector reaches nominal temperature
Sector 4-5 of the LHC has now been cooled with superfluid helium to a temperature of 1.9 K (−271.3 °C)
LS2 Report: first beam inside the upgraded HIE-ISOLDE facility
Upgrades and repairs of the HIE-ISOLDE linear accelerator will enable experiments to delve deeper than ever into the physics of radioactive isotopes
LS2 Report: waiting for antiprotons...
In the AD hall, a beam of H- ions has reached the GBAR and ALPHA experiments, marking the end of the installation of new transfer lines from the ELENA deceleration ring
Completion of pressure tests in the LHC
The final pressure test in the LHC took place in sector 6-7 on 27 October. The pressure tests are the last step before the cooling of each sector
The PS key has been handed back to the Operations group
On 23 October, the PS returned to the Operations group’s hands. Beam commissioning in the accelerator is scheduled for 1 March 2021
LS2 Report: increased cryogenic power at LHC Point 4
At LHC Point 4, a refrigerator that cools helium from room temperature to 4.5 K (-268.65 °C) has undergone major improvements in preparation for the HL-LHC
LS2 Report: All interconnections in the LHC have been closed
The DISMAC project is coming to an end: the last of the 1232 interconnections was closed in August and the cool-down of the machine will now begin
LS2 Report: CERN’s newest accelerator awakens
Linac 4 has taken over from the retired Linac 2 as the first accelerator in the LHC injection chain
LS2 Report: Further upgrades for the PS
Two new internal beam dumps and a new septum magnet have been installed in the PS as part of the LIU project
LS2 Report: The High-Luminosity LHC is ready for injection
A new beam absorber, developed for high luminosity, has been installed in the LHC